The project timeline, updated June 2026, is below. Items in green are completed; items in yellow are in progress; items in blue are anticipated.
| |
- Project Funding Approval. Ministry of Education and Child Care approves project. [Project Agreement signed September 2024]
|
| |
- Project Tender and Award: Early Works Construction management contract awarded April 2026; subtrades awarded May 2026. [Completed: May 2026]
|
| |
- Project Design and Development. Awarded prime architectural services contract. Completed preliminary engagements with Pitt Meadows Secondary school community, Katzie First Nation, and the City of Pitt Meadows. Architects and consultants finalized the school schematic design and hosted an open house to gather additional public feedback. Architects will produce detailed construction drawings and specifications for the main building. Pre-tender approval from the Ministry of Infrastructure will be sought to proceed with construction. [In progress: October 2024 – July 2026]
|
| |
- Construction: Early Works. Construction process begins. Includes site preparation and construction of temporary parking. [In progress: June 2026 – November 2026]
|
| |
- Project Tender and Award: Main Building. Put the project out to tender, evaluate bids from construction companies, and award the project to the successful bidder. [Anticipated: October 2026]
|
| |
- Construction. Construction process begins. Includes building construction and landscaping. [Anticipated: November 2026 – June 2029]
|
| |
- New School Opens. [Anticipated: September 2029]
|
| |
- Old School Demolished and New Playfield Built.Current school facility is demolished, a new parking lot and playfield are built, and site development is completed. [Anticipated: June 2029 – June 2030]
|
| |
- Project Completion Report. [Anticipated: August 2030]
|
Download timeline in PDF
Updated June 2026
How long is construction expected to last?
Construction will be split into three phases:
- PHASE 1 (early works) will run from June to November 2026. This phase will include excavation, utility services installation, tree cutting, and soil removal in preparation for the construction of the main school building. The pick-up and drop-off zone to the north of the existing school will be adjusted to allow safe access for vehicles during construction. Trees that will not be removed will have protective fencing installed.
- PHASE 2 (main building construction) will begin in early 2027.
- PHASE 3, the final phase, will cover demolition of the old building, construction of the new parking lot and associated landscaping, followed by the demolition of the existing parking, and the construction of the new turf field. The project is expected to completed in 2030.
What changes can we expect in traffic patterns around the school during construction?
During summer 2026, the contractor will route trucks around the building in accordance with the latest traffic control plan. Once school resumes in September and through to the end of early works, the contractor will use only the east side access roadway.
Why were trees taken down?
The new school is being built on the same property while the current school stays open, so the construction footprint is tight. Trees have only been removed where the new building, utilities, and construction access required it. Every tree that can stay is staying, and those trees are getting protective fencing during construction.
Will the trees that have been removed be replaced?
Landscaping, which will include the planting of new trees, is part of the final phase of the project, which will conclude in 2030.
What measures are in place to ensure the safety of students and pedestrians near the construction site?
The contractor will adhere to all City of Pitt Meadows bylaws and WorkSafeBC regulations to ensure the highest safety standards. Additionally, safety fencing and signage will be installed around the construction site to guide and protect students and pedestrians. Regular safety inspections will be conducted to maintain a secure environment, and the construction team will work closely with the school to address any safety concerns promptly.
How will you mitigate the impact on neighbouring homes of dust from the construction site?
Measures are being implemented to prevent dust issues in the future, including continuous watering during high-dust activities and increased monitoring on weekends and during extended work hours. In addition, the City is reviewing the contractor’s dust control plan to ensure compliance with City bylaws and regulations.
What are the working hours for the construction site?
Construction site working hours are 7:00 a.m. to 9:00 p.m.
Will school operations be affected by construction noise and disruptions?
We understand that construction noise and disruptions are a concern for our school community. Construction activities are exempt from the Noise Control Bylaw Monday to Saturday, 7:00 a.m. to 9:00 p.m. To minimize impact on school operations, we will be working closely with the construction team to schedule the most disruptive activities outside of school hours whenever possible. We will provide regular updates to keep the school community informed about construction progress and any potential changes to school operations.
How will you ensure the construction site is secure during and after school hours?
The site will be fully fenced off, and security cameras installed at the perimeter of the project site. Access to the construction site will be strictly controlled, and only authorized personnel will be allowed entry.
How will emergency services access the school in case of an emergency during construction?
The general contractor for early works has prepared a comprehensive fire safety plan, which has been submitted to and approved by the Pitt Meadows Fire Department. This plan includes detailed provisions for emergency access to both the construction site and the school. We are committed to ensuring that emergency vehicles can quickly and safely reach any area of the school during construction.
As a neighbour/community member, whom can I contact if I have a time-sensitive issue after hours related to the site?
For after-hours requests, call Angel Answering Service at 604.466.4357, identify the concern, and request a callback from the manager on call.
Whom can I contact for more information or to report concerns about the construction?
If you have questions, concerns, or feedback related to construction, please do not approach the construction crew. You can submit your question or report concerns to us at projects@sd42.ca, and we will provide a response within two business days. Please include “PMSS” or “Pitt Meadows” in the subject line.
Pitt Meadows Secondary families with questions related to their child(ren) should continue to direct such questions to the school principal.