ELE Construction Updates

October 23, 2024: Eric Langton Replacement Project Update – 122nd Avenue path reopened

October 23, 2024
The foundation work near the 122nd Avenue pathway to Eric Langton Elementary has been completed and the path has been reopened for pedestrians as of Wednesday, October 23, 2024. (See  read more

September 20, 2024: Eric Langton Replacement Project Update

September 20, 2024
The district received the permit from Fortis BC on September 19, 2024, and construction of the new school is now underway, starting with excavation and foundation work. Temporary Closure of  read more

August 30, 2024: Update on Eric Langton Replacement Project

August 30, 2024
Summer Progress Work on the sediment pond on the northwest corner of the site was completed over summer break, and the pedestrian path between the school and 122nd Avenue has  read more

July 4, 2024: Temporary closure of path leading to Hinch Crescent

July 4, 2024
For safety reasons, the path that connects Hinch Crescent and the northwest side of the Eric Langton Elementary site has been temporarily closed. The path will remain closed until the  read more

June 28, 2024: ELE Replacement Project Update – northwest playground closed July 2 – 15, 2024

June 28, 2024
The construction crew will begin building the erosion and sedimentation control basin (ESC pond) on the northern side of the site early next week. For safety reasons, the adjacent playground  read more
Our vision
Our vision is for every individual to feel valued and for all learners to reach their potential.
Our mission
Our mission is to support all individuals in their development as successful learners, and as respectful, caring and responsible members of society.